NEW QUESTION 41
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost andActual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

 
 
 
 

NEW QUESTION 42
You are trying to create a custom infolet but are notable to find the “Create Infolet” option in the Infolet repository window. Whichtwosteps should be completed before you can access the “Create Infolet” option?

 
 
 
 

NEW QUESTION 43
Your organization has been awarded a new contract based on which you are allowedto sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)

 
 
 
 

NEW QUESTION 44
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)

 
 
 
 
 

NEW QUESTION 45
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China andadded a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)

 
 
 
 

NEW QUESTION 46
Identify two attributes for which you can enter budgets that will be considered for Budgetary Controls in Project Portfolio Management. (Choose two

 
 
 
 
 

NEW QUESTION 47
Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accountingclose cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.
Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)

 
 
 
 
 

NEW QUESTION 48
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project:
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want todefine deliverables for your project requirementsthat are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect. (Choose two.)

 
 
 
 

NEW QUESTION 49
You haveprojects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify the why the project transaction controls are not applied. ( Choose the best answer.)

 
 
 
 

NEW QUESTION 50
Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certainnumber of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week.
What feature would you use to meet this requirement? (Choose the best answer.)

 
 
 
 

NEW QUESTION 51
When implementing Project Performance Reporting, your customer has the following requirements:
* Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
* As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold levelrule is ideal for this kind of KPI definition? (Choose the best answer.)

 
 
 
 

NEW QUESTION 52
You havedefined two expenditure types, but they are not available for selection when youenter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)

 
 
 
 

NEW QUESTION 53
Your company creates a separate project for infrastructure services, so as to track these costs separately and then allocateto various projects that use the services of the infrastructure team. You want to allocate these costs by first attributing a fixed percentage of the source amount to each project and then spread it across tasks based on the actual labor hours charged to each task.
Which allocation basis method would you use to meet this requirement? (Choose the best answer.)

 
 
 
 

NEW QUESTION 54
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)

 
 
 
 
 

NEW QUESTION 55
Your customer has the following setups onthe project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, youperform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would thecorrect behavior of the application be after these actions? (Choose the best answer.)

 
 
 
 

NEW QUESTION 56
Identifythethreecontract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three

 
 
 
 
 

NEW QUESTION 57
After completing setups in a source environment, your customer wants to move the setup data to a target environment. Identify the two statements related to task listscope, which you must consider before taking a decision based on the customer requirement. (Choose two.)

 
 
 
 

NEW QUESTION 58
Which setup option is common to both financial and project plan types?

 
 
 
 

NEW QUESTION 59
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)

 
 
 
 

NEW QUESTION 60
Identify theattribute of a project typethatdetermines if expenditure items are billable, and theamount type to be used as the basisfor transfer pricing. (Choose the best answer.)

 
 
 
 

NEW QUESTION 61
Whichfivesteps are required for the File-Based Data Import Integration option?

 
 
 
 
 
 

NEW QUESTION 62
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these classcategories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)

 
 
 
 

NEW QUESTION 63
Your customer has separate organizationsto maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (Choose two.)

 
 
 
 
 

Latest 100% Passing Guarantee - Brilliant 1Z0-1057-21 Exam Questions PDF: https://www.test4engine.com/1Z0-1057-21_exam-latest-braindumps.html 1

Links:
  1. https://www.test4engine.com/1Z0-1057-21_exam-lates t-braindumps.html
Post date: 2022-07-04 12:37:47
Post date GMT: 2022-07-04 12:37:47

Post modified date: 2022-07-04 12:37:47
Post modified date GMT: 2022-07-04 12:37:47

Export date: Mon Nov 18 4:38:27 2024 / +0000 GMT
This page was exported from Exam for engine [ http://blog.test4engine.com ]