This page was exported from Exam for engine [ http://blog.test4engine.com ] Export date:Mon Nov 18 2:29:01 2024 / +0000 GMT ___________________________________________________ Title: Free AACE International AACE-PSP Exam 2023 Practice Materials Collection [Q64-Q78] --------------------------------------------------- Free AACE International AACE-PSP Exam 2023 Practice Materials Collection AACE-PSP Exam Info and Free Practice Test All-in-One Exam Guide Jan-2023 NO.64 Each of the following accurately describes total float in a schedule EXCEPT:  The amount of time an activity can be delayed without delaying the overall project completion time.  Can be positive or negative.  The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.  Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start. NO.65 Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?  8 work days  18 work days  7 work days  15 workdays NO.66 Which of the following are NOT normally included in the project scope statement, either directly or by reference?  Project objectives in terms of cost, schedule and quality measures  Project contract between the contractor and owner  Project justification  Project deliverables NO.67 Why does activity 1001 have two successor activities?  Because the late finish of 1001 and the late start of 7001 require two successors  Because the problem could not effectively work with only one successor  Because there are two defined logic paths for the work  Because the duration of activities 2001, 2002 and 200.f require two successors NO.68 Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:  Predecessor is activity 5001, successor is activity 8001  Predecessor is activity 4001, successor is activity 8001  Predecessor is activity 9001, successor is activity 9002  Predecessor is activity 5001, successor is activity 8002 NO.69 Project delays are best analyzed  After either the contractor or the owner acknowledges ^responsibility for the delay.  Contemporaneously with the delay.  By an expert after the project is finished when complete records are available and the impact is known.  Late in the project. NO.70 How many work days does it take to move the product from testing to sale?  60.  70.  100.  90. NO.71 The linear scheduling velocity diagram has the following two-axis:  Location and crew size  Time and location  Time and rate of progress  Time and crew size NO.72 Time-scaled logic diagrams are  Only calculated using a computer.  The same as a pure-logic diagram.  Used to calculate the most probable activity duration.  Logic networks that are drawn to match the calendar. NO.73 Using the “normal” schedule, what is the early finish date of activity 10002 and its total float?  12-27-03 and 24 days of float  12-18-03 and 4 days of float  12-17-03 and 4 days of float  12-18-03 and 25 days of float NO.74 Which of the following is NOT true?  Remaining durations can exceed original durations.  Constraints can interfere with the longest path calculation.  Multiple calendars can affect the total float calculation.  A network must contain only one Critical Path. NO.75 When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?  Detailed listing of working days for each calendar used  Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID  Assigned party responsibility for each work task  Tabular listing of activities showing duration, calendar ID, early and late dates NO.76 Which is NOT an industry-recognized methodology for quantifying critical delay?  Gantt Chart.  Periodic Windows.  Collapsed As-Built.  Time Impact. NO.77 During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?  Delay product release by 5 days.  Expedite packaging by 5 days.  Expedite printing by 5 days.  Delay manufacturing by 5 days. NO.78 An early start constraint dictates  An activity’s remaining duration.  The planned start of a successor activity  The planned start of an activity.  The actual start of an activity.  Loading … Pass AACE International AACE-PSP Actual Free Exam Q&As Updated Dump: https://www.test4engine.com/AACE-PSP_exam-latest-braindumps.html --------------------------------------------------- Images: https://blog.test4engine.com/wp-content/plugins/watu/loading.gif https://blog.test4engine.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2023-01-31 10:51:08 Post date GMT: 2023-01-31 10:51:08 Post modified date: 2023-01-31 10:51:08 Post modified date GMT: 2023-01-31 10:51:08