NEW QUESTION 57
An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?

 
 
 
 

NEW QUESTION 58
You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

 
 
 
 

NEW QUESTION 59
You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder’s conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

 
 
 
 

NEW QUESTION 60
Where are negative risks recorded?

 
 
 
 

NEW QUESTION 61
A Project Manager is in the execution phase of a highly visible project and a major milestone is due in three weeks. The Project Manager has discovered that a vendor’s deliverable for this milestone will be five weeks late. What should the Project Manager do?

 
 
 
 

NEW QUESTION 62
All of the following are resources that you will need to monitor and control in a program environment except for which one?

 
 
 
 

NEW QUESTION 63
Which of the following statements is most accurate about the critical path?

 
 
 
 

NEW QUESTION 64
You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

 
 
 
 

NEW QUESTION 65
The program manager must define the program and understand the organization’s target market and customer needs. What should the program manager do first?

 
 
 
 

NEW QUESTION 66
You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

 
 
 
 

NEW QUESTION 67
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.
Where should the program manager document this?

 
 
 
 

NEW QUESTION 68
A municipal agency manages a city’s water and wastewater infrastructure. Its six-year capital improvement program (CIP) is approximately US$4 billion, and is used for such things as improving aging infrastructure, addressing regulatory requirements, and upgrading facilities. The mayor and key stakeholders are concerned because of yearly rate increases for residents. After receiving proposals from program managers for this key program, which is half of the current CIP, a program management team is hired and receives an approved business case.
What should the project manager do next?

 
 
 
 

NEW QUESTION 69
You are the program manager for your program and are creating a communications management plan.
Management wants you to address the type of communications based on the number of communication channels you’ll have within the program. Currently there are 345 stakeholders in your program but next week you’ll have 387 stakeholders. How many more communication channels will you have next week in your program?

 
 
 
 

NEW QUESTION 70
Who prepares the statement of work (SOW) for external projects?

 
 
 
 

NEW QUESTION 71
A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.
Which document will be created to support this activity?

 
 
 
 

NEW QUESTION 72
A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.
What should the program manager do next?

 
 
 
 

NEW QUESTION 73
You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?

 
 
 
 

NEW QUESTION 74
What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

 
 
 
 

NEW QUESTION 75
What is a stakeholder analysis chart?

 
 
 
 

NEW QUESTION 76
All of the following information is defined in the program statement of work except for which one?

 
 
 
 

Free PMI Certification PgMP Exam Question: https://www.test4engine.com/PgMP_exam-latest-braindumps.html

         