CCM Braindumps Real Exam Updated on Aug 22, 2026 with 142 Questions [Q61-Q77]

Rate this post

CCM Braindumps Real Exam Updated on Aug 22, 2026 with 142 Questions

Latest CCM PDF Dumps & Real Tests Free Updated Today

Medical Professional CCM Exam Syllabus Topics:

Section Objectives
Topic 1: Psychosocial and Support Systems – Psychosocial assessment
– Community resources and support systems
Topic 2: Rehabilitation and Disability Management – Rehabilitation principles
– Return-to-work planning
Topic 3: Quality and Outcomes Evaluation – Quality improvement methods
– Outcome measurement and evaluation
Topic 4: Ethics, Legal, and Regulatory Aspects – Professional ethics in case management
– Legal and regulatory compliance
Topic 5: Care Delivery and Reimbursement Methods – Healthcare delivery systems
– Insurance and reimbursement structures

 

NO.61 Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

 
 
 
 

NO.62 Towards the end of implementing a varied work (initiated originally by the Contractor as a ” Value Engineering Proposal ” , relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation?
[FIDIC Red Book, 2017 Edition]
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NO.63 The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NO.64 You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer- a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NO.65 Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NO.66 (You are the Contract Manager of the Employer ‘ s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))

 
 
 
 

NO.67 In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

 
 
 
 

NO.68 Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NO.69 (Under the FIDIC Red Book, which of the following statements are correct? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).)

 
 
 
 
 

NO.70 (In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

 
 
 
 

NO.71 Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?

 
 
 
 

NO.72 (Which one of the following statements regarding FIDIC Golden Principles is correct?)

 
 
 
 

NO.73 A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

 
 

NO.74 Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor’s Proposal. Which two of the following statements are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NO.75 You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
The Employer demands perfection in the project’s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?

 
 
 
 

NO.76 (Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ‘ s Requirements. Which statement is correct?)

 
 
 
 

NO.77 Under the FIDIC Construction Contract, which one of the following statements is correct?

 
 
 
 
 

CCM Dumps With 100% Verified Q&As – Pass Guarantee or Full Refund: https://www.test4engine.com/CCM_exam-latest-braindumps.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below